Under Construction: Hunter Mill Road over Colvin Run Bridge Replacement in Fairfax County
Cost and schedule ►
Traffic alerts ►
Public outreach ►
Please note: Hunter Mill Road traffic shifted onto a portion of the new bridge over Colvin Run Dec. 30. One lane of alternating traffic is traveling across the newly constructed portion of the bridge while the old bridge is demolished and the remaining portion of the new bridge is built. There is no posted weight limit for the current bridge.
Update: This is now scheduled for Fri 12/30 at 2PM. https://t.co/wsExiAvlq0
— VDOT Northern VA (@VaDOTNOVA) December 28, 2022
Temporary traffic signals and Driveway Assistance Devices are in place along Hunter Mill Road just north and south of Colvin Run until later this spring, read more in the traffic alert.
Vienna: Around noon Wed 9/14, temporary traffic signals and Driveway Assistance Devices (DADs) will be activated along Hunter Mill Rd in the area of Colvin Run to allow construction to continue on the new bridge. Sadly, these DADs won't have jokes. More: https://t.co/RnOKQkydae pic.twitter.com/aZACjX6nUw
— VDOT Northern VA (@VaDOTNOVA) September 12, 2022
This project is replacing the old weight-restricted, one-lane Hunter Mill Road (Route 674) bridge over Colvin Run that was built in 1974. The new bridge will have two lanes separated by a median/splitter island.
The project also includes:
- An improved trail crossing south of the bridge
- Landscaping in the median/splitter island
- Abutments for a new trail bridge over Colvin Run (Fairfax County will construct the trail bridge in the future)
Hunter Mill Road averages 7,400 vehicles a day within the project limits.
Estimated Costs
Preliminary Engineering - $1 million
Construction - $4.2 million
Total: $5.2 million
This project is financed with federal, state (including State of Good Repair funds used for bridges) and Fairfax County funding.
Benefits
The project aims to reduce congestion and improve operations and safety.
Major Milestones
Public Information Meeting - April 2018
Virtual Public Involvement - May/June 2020
Virtual Design Public Hearing - September 2020
Advertise for Construction - February 2021
Award Construction Contract - April 2021
Begin Construction - August 2021
Final Completion - Late Spring 2023
Resources
Oscar Jamilla, DPE, PMP
Construction
703-259-2769
Chan Basnayake, P.E., PMP, CCM
Construction
703-259-2947
Other relevant links:
Construction Start News Release - August 2021
Virtual Design Public Hearing
Video, Presentation, Comment Sheet, Ad and Webpage - September 2020
Project Plans - June 2020
Conceptual Bridge Replacement Study Report - October 2017
Major funding source: State of Good Repair
Phase: Under Construction
UPC: 110499, 110433
State ID: 0674-029-358, P101, B643
Lat/Long: 38.965604, -77.309634
Locality:
Fairfax