Under Construction: Denbigh Boulevard Bridge Replacement

Cost and schedule ►


Traffic alerts ►

This project will replace the structurally-deficient Denbigh Boulevard Bridge over Interstate 64 and CSX Railway between Warwick Boulevard and Jefferson Avenue in Newport News with a new bridge that meets current geometric and design standards.

The project includes demolition of the existing bridge, and construction a new bridge with four 12-foot lanes, a 16-foot raised median and two 8.5-foot sidewalks, as well as new roadway approaches and stormwater management facilities.

The demolition and construction is being completed in two stages to maintain one lane of traffic in each direction on Denbigh Boulevard throughout construction. In the first stage, traffic has been shifted to one lane in each direction on the existing bridge, while demolition work and construction of the new bridge, roadway, retaining wall and stormwater pond are underway. In the second stage, traffic will be shifted to the newly constructed portion of the bridge, allowing crews to complete the remaining demolition and construction work.

Traffic Impacts

Motorists will be advised of lane closures and traffic shifts that occur during the project, which is scheduled for completion in spring 2022. All construction work is dependent upon weather conditions.

Denbigh Boulevard Stage 2 Traffic Configuration (June 2021-Spring 2023) 

As of June 2021, crews have completed the first stage of the bridge replacement project consisting of the demolition and the reconstruction of the eastbound Denbigh Boulevard overpass bridge. In order to demolish and replace the existing westbound overpass bridge in the next stage of construction, both directions of traffic between Pocahontas Drive and Millwood Drive were shifted from the westbound section of the bridge over to the newly constructed eastbound bridge. 

To learn more about this traffic configuration and second stage of construction, read the full news release here: "CLOSURES AND TRAFFIC SHIFT SCHEDULED FOLLOWING COMPLETION OF NEW SECTION OF DENBIGH BOULEVARD BRIDGE"

Full Closure on Richneck Road (August 2019-Spring 2023)


During construction, a long-term closure with a signed detour remains in place on Richneck Road at the Denbigh Boulevard intersection to accommodate the lane reductions and reconstruction of the intersection at Richneck Road.

  • As of August 6, 2019, access to and from Denbigh Boulevard to Richneck Road is currently prohibited for the remainder of the project (pictured below). Signed detours are in place directing Richneck Road and Denbigh Boulevard traffic to use Jefferson Avenue.

Richneck Road Detour Map 

Full Closure on Denbigh Boulevard (Nightly July 5-7, Weather Permitting*)

Starting as early as July 5 through the morning of July 8, overnight full closures are scheduled to be in place between 7 p.m. and 6 a.m. on Denbigh Boulevard, between Pocahontas Drive and Millwood Drive, to allow for the setting of bridge girders on the new spans of new westbound section of the Denbigh Boulevard overpass over I-64. A signed detour will be in place directing motorists traveling along Warwick Boulevard and Jefferson Avenue to use Bland Boulevard as an alternate route. 

*This construction work is weather- and schedule-dependent; therefore, this schedule is subject to change.

For more information on scheduled traffic impacts for this work, read the full traffic alerts here: 

JULY 1, 2022: "FULL OVERNIGHT CLOSURES SCHEDULED NEXT WEEK ON DENBIGH BOULEVARD OVERPASS BRIDGE OVER I-64"

June 23, 2022: "FULL OVERNIGHT CLOSURES ON DENBIGH BOULEVARD BRIDGE OVER I-64 EXTENDED ONE NIGHT DUE TO WEATHER"

June 16, 2022:
"FULL OVERNIGHT CLOSURES SCHEDULED TO BEGIN NEXT WEEK ON DENBIGH BOULEVARD OVERPASS BRIDGE OVER I-64" 

Benefits 

The project will upgrade the interstate overpass to meet current design standards. 

Major Milestones 

Estimated Schedule

Design began in 2015, followed by right-of-way acquisition in 2016. The project was advertised for construction in fall 2018, with a notice to proceed issued on March 18, 2019.

The $23 million construction contract was awarded to Corman Kokosing Construction Company of Annapolis Junction, MD on January 16, 2019.

The estimated* schedule for the project is as follows:

1st Stage of Construction - Denbigh Boulevard traffic shift: April 2019 - Spring 2021
Section of I-64 noise barrier temporarily removed: Summer 2019 - Fall 2021
Full Richneck Road Closure Begins: August 6, 2019 through Spring 2023
2nd Stage of Construction Begins - Denbigh Boulevard traffic shift: Spring 2021 - Spring 2023
Estimated Completion Date: Spring 2023
*Project work and scheduled closures are dependent upon weather conditions and other factors.

Resources

Contact Info:

Hampton Roads Public Affairs
(757) 956-3029

 


Newsletters:

Other relevant links:

Noise Study Analysis Memorandum

Previous Meetings >>

Phase: Under Construction

UPC: 93077

Lat/Long: 37.135556, -76.525884

Locality: Newport News

Page last modified: July 1, 2022