Under Construction
Route 42 and Mt. Crawford Avenue - Bridgewater |
Project at a Glance
Begin Date
Spring 2008
Est Completion Date
October 31, 2008
Cost
$481,874.50
Contractor
Howdyshell Excavating Inc. of Mount Solon, Va.
Locality
Rockingham
District
Staunton
Spring 2008
Est Completion Date
October 31, 2008
Cost
$481,874.50
Contractor
Howdyshell Excavating Inc. of Mount Solon, Va.
Locality
Rockingham
District
Staunton
Contact
Don Komara
(540) 434-2586
Project Details
Intersection improvements in the Town of Bridgewater. The project is located at Route 42 and Mount Crawford Avenue and includes right-turn lanes on Mount Crawford Avenue and Route 42, plus sidewalk improvements.Contacts
Don Komara, (540) 434-2586Page last modified: Friday, May 02, 2008