Project at a Glance

Begin Date
Early 2015

Cost
Estimated Cost – $1,189,130

Lengths and Limits
0.1-mile long From 0.45 west of Route 717 To: 0.55 west of Route 717

Locality
Alleghany

District
Staunton

Contact
Heather Williams
540-332-9204

Project Details

The proposed project is located on Route 159 (Dunlap Creek Road) at the bridge over Crow Run in Alleghany County.  The project is 0.1-mile long with its limits extending from 0.45 west of Route 717 to 0.55 west of Route 717.  The proposed project will replace the deteriorated Crow Run bridge.

The existing bridge is 23-feet long and 24-feet wide with two 11-foot lanes with two-foot shoulders.  The adjacent roadway is composed of two 11-foot travel lanes with one-foot shoulders.

The new structure will be a box culvert with two 11-foot travel lanes and four-foot shoulders.  Guardrail is proposed on the four corners of the new structure.

During construction traffic will use a temporary detour structure and access road which will be constructed to the south of the existing bridge.  The temporary detour will be composed of a single-lane roadway controlled by traffic signals.

The traffic volume at this location is 852 vehicles per day.  The projected traffic volume in 2029 is 980 vehicles per day, of which 5.7 percent will be trucks.

The total estimated cost for this project is $1,189,130, including $265,141 for preliminary engineering, $80,000 for right of way and $843,989 for construction.

What’s Next

Preliminary Engineering   Summer 2013
Right of Way  Fall 2013
Construction  Early 2015

Media and Public Events

Design Public Hearing
Tuesday, June 18, 2013, 4-6 p.m.
Dunlap Volunteer Fire and Rescue Squad
Hematite Fire Department Building
5519 Dunlap Creek Road
Covington, VA 24426

Benefits of Project

Safety will be improved by replacing a deteriorating bridge structure with a new box culvert.

During Construction

During construction traffic will use a temporary detour structure and access road which will be constructed to the south of the existing bridge.  The temporary detour will be composed of a single-lane roadway controlled by traffic signals.

Traffic Alerts

Traffic alerts can also be found on the VDOT website under Travel Center, Travel advisories and lane closures. Click on the area of the state you are interested in, and view current travel advisories and lane closures. Click here to go to the Staunton District Travel Center page:  Staunton District

Real-time traffic information is available on the VDOT 511Virginia.org website and also by calling 511 on your landline or wireless phone.  Click here to go to 511:  Virginia 511 Web

Project Numbers

State  0159-003-619, P101, R201, M501, D608
Federal  BR-003-8(130), BR-003-8(131), BR-003-8(132)
UPC  90189

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Dec. 19, 2014