Under Construction: Tenth Street Improvements - Roanoke

Cost and schedule ►


Traffic alerts ►

Public outreach ►

Increasing traffic volumes and safety concerns for vehicles, pedestrians and bicycles have prompted VDOT and the City of Roanoke to pursue improving the section of 10th Street between Fairfax Avenue and Williamson Road.

Right of way was purchased and the improvements were divided into two separate construction projects.  The first project, phase one, starts just south of Fairfax Avenue and extends 0.78 mile to just north of Andrews Road.  The second project, phase two, will start at Andrews Road and extend 0.93 mile to Williamson Road.

Phase one of the project between Fairfax Avenue and Andrews Road was funded and began in May 2016.  Phase two of the project between Andrews Road and Williamson Road was awarded in February 2017.

To view a larger version of the plan below, click here.

Tenth Street Improvements - Roanoke

Phase Two - UNDER CONSTRUCTION: Andrews Road and Williamson Road

Phase two is a $10.7 million dollar project along the 0.9-mile section of Tenth Street in Roanoke from Andrews Road to Williamson Road. This phase of the project will improve traffic flow and safety for vehicles, pedestrians and bicyclists.

Improvements will include reconstructing the two travel lanes and providing bicycle lanes, curb and gutter, and sidewalks. Traffic signals are also being added or replaced at Tenth Street’s intersections with Hunt Avenue and Williamson Road and turn lanes will be added at the Tenth Street intersection with Hunt Avenue.

Work in Progress:

  • Utility work is completed and drainage curb inlets are being set between Hunt and Andrews Road.
  • Curb and Gutter and entrances are being constructed between Levelton Avenue and Andrews Road. Incidental concrete items such as sidewalk, steps and driveways to be completed fall of 2019.
  • Roadway grading and stone placement ongoing between Greenhurst Ave and Andrews Road.
  • Williamson Road and 10th Street signal installation. Completion: fall 2019.
  • Hunt Avenue and 10th Street signal installation. Completion: fall 2019.
  • When completed, base and intermediate asphalt will be placed. Completion: fall 2019.

Upcoming Schedule of Work:

  • Remainder of curb, gutter, sidewalk and steps. Completion: fall 2019.
  • Final paving and marking. Completion: fall 2019.
  • Landscaping installation. Completion: fall 2019.

Work on the project began in summer 2017 and is expected to be completed in fall 2019.


Phase One - COMPLETED: Fairfax Avenue and Andrews Road

Phase one was a $12-million project from south of Fairfax Avenue to just north of Andrews Road. This phase improved the existing roadway, widened travel lanes, updated signal equipment, provided curb and gutter, sidewalks and bike lanes. Turn lanes were added at 10th Street’s intersections with Hunt Avenue, Grayson Avenue and Orange Avenue. Additional improvements improved the safety and flow of traffic through the area while developing a bicycle/pedestrian friendly environment.  Lick Run and the Lick Run Greenway now pass through a concrete arch under 10th Street.

Work began in summer 2016 and was completed in summer 2018. 

Benefits 

The benefits of this project focused on improving the safety and flow of traffic through the area while developing a bicycle/pedestrian friendly environment. 

Resources

Contact Info:

Sid Scott
540-589-6307

Phase: Fairfax Avenue to Andrews Road and Andrews Road to Williamson Road

Lat/Long: 37.282763, -79.954664

Locality: Roanoke

Page last modified: Nov. 4, 2019