Route 114 Widening - Christiansburg

Project at a Glance

Begin Date
Spring 2012

Est Completion Date
Summer 2015

Phase
Under Construction

Cost
$24.5 million

Contractor
DLB Inc.

Locality
Montgomery

District
Salem

Contact
Ricky Keith
540-381-7201
Media Contact - Jen Ward
540-387-5238

What's Being Done?

This project will widen one mile of Route 114 (Peppers Ferry Road) at New River Valley Mall in Christiansburg from two to four lanes with turn lanes and improve access management by installing a raised median. 

The project also will include relocating the signal at the mall entrance and building a new Huckleberry Trail bridge over Route 114. 

PROJECT UPDATE:
Route 114 is open to traffic.

Handrails are being fabricated for the Huckleberry Trail bridge. Once the handrails arrive and are installed, the bridge will be open to the public. The estimated completion is in summer 2015.

Lighting is currently being installed in the area and other incidentals including landscaping will be in process this spring. 

There are currently no other traffic impacts expected on this project.
 