Map of construction project districts

In Design

Elliston/Ironto Connector - Montgomery County

Route 603 Reconstruction

Project at a Glance

Begin Date
Advertisement date 2013

Cost
$17 million

Lengths and Limits
Route 11/460 to I-81 at exit 128 (Ironto)

Locality
Montgomery

Contact
Jesse Weitzenfeld
540-387-5353

What's being done?

The purpose of the proposed Ironto/Elliston connector project is to reconstruct Route 603 (North Fork Road) in Montgomery County to current standards to improve safety and capacity.  

This project would provide a better connection between Route 11/460 and Interstate 81 at exit 128.  The current cost estimate is $17 million.  

The proposed project would provide two 12-foot travel lanes with eight-foot shoulders and retaining walls.

A design public hearing was held on Thursday, May 19, 2011.  Here are links to the brochure and displays presented at the public hearing.

 

 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Oct. 14, 2012