Recently Completed
Powhite Parkway Extension Concrete Repairs, Chesterfield |
| Deteriorated pavement removed and replaced |
Project at a Glance
Begin Date
April 2011
Est Completion Date
May 2012
Cost
$7.8 million
Lengths and Limits
9.5 miles
Locality
Chesterfield
District
Richmond
April 2011
Est Completion Date
May 2012
Cost
$7.8 million
Lengths and Limits
9.5 miles
Locality
Chesterfield
District
Richmond
Contact
Mike Wells
804-524-6210
What was done
Deteriorated sections of pavement along Route 76 were removed and replaced with concrete between Charter Colony Parkway and Richmond city limits.
Page last modified: Oct. 14, 2012