Recently Completed
Route 33 at Route 54, Hanover |
Intersection Improvements |
Area Maps
Project at a Glance
Begin Date
February 2013
Est Completion Date
November 2013
Cost
$3.4 million (construction)
Lengths and Limits
0.337 miles west of relocated Rt. 54 to 0.174 miles east of relocated Rt. 54
Locality
Hanover
District
Richmond
February 2013
Est Completion Date
November 2013
Cost
$3.4 million (construction)
Lengths and Limits
0.337 miles west of relocated Rt. 54 to 0.174 miles east of relocated Rt. 54
Locality
Hanover
District
Richmond
Contact
Doug Kisamore, project manager
804-752-4772
Project Description
The project shifted Route 33 to the east and added turn lanes. Motorists on Route 33 now have through travel access to continue on Route 33 or enter Route 54. Additionally, cul-de-sacs were constructed on the existing Route 33 and Route 54 near the intersection.
The project was completed in November 2013.
Page last modified: March 21, 2014