Map of construction project districts

Recently Completed

Intersection Improvements at Courthouse and Laurel Spring Roads in Prince George

Turn lanes and new traffic signals to provide improved safety and traffic flow
Project at a Glance
Begin Date
August 2017

Est Completion Date
Winter 2017-18

Phase
Complete

Cost
$1.1 million

Contractor
J.R. Caskey, Inc.

Locality
Prince George

District
Richmond

Contact
Ron Hobson, P.E.
804-862-6450

Project Description

Crews constructed a northbound right turn lane on Courthouse Road (Route 106) to Laurel Spring Road (Route 616) and replaced the intersection’s traffic signals to accommodate the new travel movement. The work will improve safety and traffic flow at this busy local intersection.

Work was completed in December 2017.

 