Cedar Level Road improvements in Hopewell

Project includes added lanes and sidewalks
Project at a Glance
Begin Date
November 2018

Est Completion Date
Spring 2020

Phase
Under Construction

Cost
$11 million

Locality
Hopewell

District
Richmond

Contact
J. Blake Smith
(804) 920-4492

What's Being Done

The project will widen Cedar Level Road between Cobblestone Parkway and Miles Avenue in the City of Hopewell. It will widen the road from two to three lanes with the addition of turn lanes, bike lanes and sidewalk. In addition, the project will realign the road to reduce an “S” curve.

Traffic Impacts

Travelers can expect intermittent lane and shoulder closures for the duration of the project. Work will include both daytime and nighttime lane closures during off-peak travel times.

Public Involvement

A citizen information meeting was held on April 22, 2015 at Hopewell High School. 

A fact sheet is available. 