Under Construction: Wilson Boulevard over Route 50 in Fairfax County

Cost and schedule ►


Traffic alerts ►

Public outreach ►

This project is rehabilitating the one-way bridge linking the eastbound Route 50 (Arlington Boulevard) service road to eastbound Wilson Boulevard. The bridge was built in 1958.

The improvements include:

  • New concrete bridge deck and steel beams.
  • Reconstructing the bridge's existing sidewalk.
  • New sidewalk along the opposite side of the bridge.
  • Upgrading the bridge railings.
  • Improving curb and gutter on the southwestern approach to the bridge.
  • New concrete end walls on the southwestern approach.

Within the project limits, Wilson Boulevard averages 7,500 vehicles a day and Route 50 averages 51,000.

Estimated Costs
Preliminary Engineering - $600,000
Construction - $3.2 million
Total - $3.8 million

This project is being financed with state and federal State of Good Repair funds used for maintenance of structures and bridges.

Benefits 

This project aims to improve safety for drivers and pedestrians and extend the overall life of the bridge.

Major Milestones 

Begin Preliminary Engineering - August 2017
Public Information Meeting - April 2018
Advertise for Construction - November 2018
Begin Construction - March 2019
Full Closure of Route 50 for a Weekend - Late Summer 2019
Estimated Completion - Winter 2019/20

Resources

Major funding source: State of Good Repair

Phase: Under Construction

UPC: 111320, 114152

State ID: 0613-029-380, P101, B647

Federal ID: STP-BR09 (297), STP-BR09 (298), NHPP-5A01 (981)

Long/Lat: 38.872090, -77.155197

Locality: Fairfax