Map of construction project districts

Under Construction

Twin Lakes Drive Bridge Replacement

Widening the bridge over Johnny Moore Creek in Fairfax County

Area Maps

Project Photos

Project at a Glance

Begin Date
June 25, 2014

Est Completion Date
Re-opened to traffic August 29, 2014; overall completion scheduled September 17, 2014

Cost
$1 million total

Contractor
Fort Myer Construction Corporation

Locality
Fairfax

District
Northern Virginia

Contact
Dinesh Singh, P.E.
Constructing Manager
703-259-2216
Chan B. Basnayake, P.E., PMP
Area Construction Engineer
703-259-2947

Note: The bridge re-opened to traffic on August 29, 2014. View release

About the Project

This project is replacing the Twin Lakes Drive bridge over Johnny Moore Creek, originally built in 1920. It includes widening the bridge to match the 22-foot roadway approach and a two-foot shoulder, bringing the total width of the bridge to 26 feet. The replacement is a single-span slab bridge.   

View this presentation for more details. 

State Project: 3546-029-751, P101, C501
Federal Project: BROS-5401(907) UPC: 87728

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Sept. 2, 2014