Shreve Road Corridor Study

Safety and operational improvements in Fairfax County

Area Maps

Project at a Glance
Begin Date
March 2020

Est Completion Date
Late Fall 2020

Phase
Study

Cost
$100,000

Lengths and Limits
Rt 29 to Rt 7 (over 2 mi)

Locality
Fairfax

District
Northern Virginia

Contact
Amir Shahpar, P.E.
Planning

Andrew Beacher, P.E.
Preliminary Engineering

About the Study

This study is assessing potential safety and operational improvements along more than two miles of Shreve Road (Route 703) between Route 29 (Lee Highway) and Route 7 (Leesburg Pike). 

The study is addressing community concerns related to speeding, pedestrian safety, sight distance and drainage. 

The following priority areas along the corridor have been identified:

  • The curve west of Oldewood Drive
  • Shrevewood Elementary School
  • Washington & Old Dominion Trail crossings
  • The curve between Chestnut Street and Hickory Street

Shreve Road averages up to 10,000 vehicles a day within the study limits.

Schedule
Begin Study - March 2020
Public Involvement - Early Fall 2020
Study Completion - Late Fall 2020

Resources

Study Overview