Map of construction project districts

Under Construction

Route 50 Widening

From Route 28 in Fairfax to Poland Road in Loudoun

Area Maps

Project Photos

Project at a Glance

Begin Date
Sept. 2011

Est Completion Date
Nov. 2015

Cost
Approximately
$94.9 million

Contractor
Shirley Contracting

Locality
Fairfax and Loudoun

District
Northern Virginia

Contact
Larry Tomlinson, P.E., L.S.
Design Build Manager
703-259-2304
Bill Atkins, CCM
Construction Manager
703-259-2939
Shirlene Cleveland, P.E.
Program Manager for Design Build Projects
703-691-6710

About the Project

Route 50 is being reconstructed and widened from four to six lanes between Poland Road and Route 28 (about 3.7 miles). In addition, VDOT is also:

• Improving traffic signalization
• Improving turn lanes
• Providing a shared-use path on both sides of the road
• Providing crosswalks with curb ramps and pedestrian signals
• Widening and upgrading bridges

Route 50 narrows from six lanes to four just west of Route 28. Increased development and congestion in Loudoun County in recent years now leads to backups during much of the day on the existing four-lane segment, especially during morning and evening rush hours. 

This project aims to relieve current and anticipated congestion, to provide pedestrian and cyclist accommodations, and to improve safety along the corridor. The road will also be more level and provide wider buffers between travel lanes and roadside hazards.

The current project cost is estimated at about $94.9 million:

• $10.0 million for preliminary engineering
• $19.0 million for right of way acquisition
• $10.5 million for utility relocation
• $55.4 million for construction 

The entire project is scheduled for completion in November 2015.

Traffic Impacts

Regular closures: Drivers can expect periodic traffic shifts, daytime lane closures 9 a.m. to 3 p.m. in each direction, and some occasional overnight lane closures.

A third lane opened to westbound traffic through the entire project on Dec. 18, 2014. Read the release

A third lane opened to eastbound traffic through the entire project on August 28, 2014. Read the release

Upcoming Project Milestones

  • Complete spur ramp construction and switch traffic between Lee Road and Route 28 - Second Quarter 2015
  • Complete westbound permanent roadway and switch traffic between Pleasant Valley Road (Fairfax) and Lee Road - Second Quarter 2015
  • Complete median construction between the Cub Run bridge and Route 28 - Third Quarter 2015
  • Substantial completion (completion of trails, signals, final paving and striping) - Fourth Quarter 2015

Resources

Construction updates: Dec. 2014 Sept. 2014 | May 2014 | April 2014 | Aug 2013
Project presentation (June 2014)
Environmental document (Categorical Exclusion)
Presentation from "pardon our dust" meeting held in June 2012
Public Hearing brochure, presentation, and summary of comments (Feb. 2009)
Public hearing display boards 1 | 2 | 3 | 4 | 5 | 6

UPC: 68757 State Project: 0050-96A-101, P101, R201, C501 
Federal Project: STP-5401(571)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Jan. 23, 2015