Under Construction

Route 1 Widening

Marys Way to Annapolis Way in Prince William County

Area Maps

Project Photos
Project at a Glance
Begin Date
May 2016

Est Completion Date
Fall 2019

Cost
$165 million

Contractor
Utilities Ductbank:
Martin and Gass

Widening:
Fort Myer Construction

Locality
Prince William

District
Northern Virginia

Contact
Oscar Jamilla, DPE, PMP
Construction

Chan Basnayake, P.E., PMP, CCM
Construction

About the Project

Route 1 (Jefferson Davis Highway) is being widened from four to six lanes between Marys Way and Annapolis Way. 

The project includes:

  • Enhanced access to the Woodbridge Virginia Railway Express kiss-and-ride facility
  • A new Route 1 bridge at Marumsco Creek
  • Improvements to Occoquan Road, including a median and turn lanes from Route 1 to south of Horner Road
  • Additional through and turn lanes on Route 1 and Occoquan Road to improve traffic operations
  • A ten-foot shared-use path and six-foot sidewalk
  • Demolition of several vacant buildings along the corridor

Route 1 averages 38,000 vehicles a day within the project limits. Projected volumes for 2036 are 75,000 vehicles per day.

Schedule
Design Public Hearing - March 2011
Prince William Board Utilities Resolution - December 2013
First "Pardon Our Dust" Meeting - March 2015
Second "Pardon Our Dust" Meeting - April 2016
Begin Construction - May 2016
Final Completion - Fall 2019

Estimated Costs
Preliminary Engineering: $11 million
Right of Way Acquisition and Utility Relocation (Including Utilities Ductbank Design and Construction): $97 million 
Construction: $56 million
Total: $165 million

This project is financed with federal, state and county funding.

Traffic Impacts

Drivers can expect daytime and nighttime lane closures on Route 1.

Lane closures are required for paving, as well as to install water main, sewer, and drainage facilities.

Bridge construction over Marumsco Creek, retaining wall work near Occoquan Road and excavation and grading work for Occoquan Road and southbound Route 1 are ongoing. 

The new connector road (across from McCormick Paints) at the northern end of Easy Street is open to traffic; the connector road that fed into the CVS parking lot is permanently closed. 

Daytime lane closures can be expected Mondays through Thursdays, 9:30 a.m. to 3 p.m., and Fridays, 9:30 a.m. to noon.

Nighttime lane closures, when necessary, will be from 9 p.m. to 5 a.m. Monday to Friday, 9 p.m. to 9 a.m. Friday to Saturday, 9 p.m. to 8 a.m. Saturday to Sunday and 9 p.m. to 5 a.m. Sunday to Monday.

Motorists should expect delays and are advised to use alternate routes.

Resources

"Pardon Our Dust" Meeting - April 2016

"Pardon Our Dust" Meeting for Utilities Ductbank - March 2015

Prince William County Board Resolution for Undergrounding Utilities - December 2013 

Design Public Hearing - March 2011 

Environmental Documents:

Project Numbers
State: 0123-076-F29, P101, R201, C501, B604, B605; 0001-076-171, R201, C501; 0123-076-004, C501, B606; 0123-76-080
UPCs: 14693, 105798, 94102, 100938
Federal: STP-111-1 (114), STP-123-9 (002), STP-5401 (621), NHPP-5A01 (644)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: March 27, 2019