Map of construction project districts

In Design

Rolling Road Widening

Improvements from Viola Street to Old Keene Mill Road in Fairfax County

Area Maps

Project at a Glance
Begin Date
Phase 1 Construction:
Fall 2019

Phase 2 Construction: 2022

Est Completion Date
Phase 1: Fall 2020

Phase 2: 2024

Phase
In Design

Cost
$56.1 million

Lengths and Limits
Viola St to
Old Keene Mill Rd

Locality
Fairfax

District
Northern Virginia

Contact
Hamid Misaghian, P.E.
Location and Design

Andrew Beacher, P.E.
Preliminary Engineering

Note: The Noise Study is now available.

Final Report, Appendices A - C, Appendix D and Appendix E

About the Project

This project aims to reduce congestion and improve safety by widening Rolling Road (Route 638) from two to four lanes between Viola Street and Old Keene Mill Road.

The project also includes a shared-use path to increase safety for bicyclists and pedestrians.

The project is being planned in a phased approach:

Phase 1 - Old Keene Mill Road intersection improvements
Includes interim improvements by adding a second left turn lane from Rolling Road to westbound Old Keene Mill Road, adding a dedicated right turn lane to eastbound Old Keene Mill Road, upgrading the signal and improving the intersection alignment.  

Phase 2 -  Widening and other improvements 
Includes widening Rolling Road from two to four lanes between Viola Street and Old Keene Mill Road, signal upgrades, pedestrian and bike facilities and improvements to access management.  

The project team has worked with Fairfax County to consider alternative design options, including the possibility of using underground utilities.

The option including underground utilities was evaluated based on feasibility, potential property impacts, cost and schedule. This option is no longer being pursued due to cost concerns.

If you would like to provide feedback at any time, send comments to meetingcomments@vdot.virginia.gov. Include “Rolling Road Widening” in the subject line.

This project is being financed with federal, state and local funding including Northern Virginia Transportation Authority funds.

Schedule
Public Information Meeting - June 2016
Public Information Meeting - November 2017
CE Reevaluation Public Notice - February 2018
Design Public Hearing - February 2018
Phase 1 Begin Right of Way Acquisition - Late Winter 2018/19
Phase 1 Begin Utility Relocation - Spring 2019
Phase 1 Begin Construction - Fall 2019
Phase 1 Construction Completion - Fall 2020
Phase 2 Begin Right of Way Acquisition - Late Winter 2018/19
Phase 2 Begin Utility Relocation - Winter 2019/20
Phase 2 Begin Construction - 2022
Phase 2 Construction Completion - 2024

Estimated Costs
Preliminary Engineering: $5.9 million
Right of Way Acquisition and Utility Relocation: $18.7 million
Construction: $31.6 million
Total: $56.1 million

Resources

Noise Study - February 2019

Final Report, Appendices A - C, Appendix D and Appendix E

Traffic Analysis Report - August 2018
Crosswalk Analysis Report - August 2018

Design Public Hearing - February 2018 (Ad)

Meeting Materials and Displays

Categorical Exclusion Reevaluation - February 2018 (Ad)

Public Information Meeting - November 2017 (Ad)

Meeting MaterialsPresentation and Displays: Noise Study Location Map | Stormwater Management Plan

Community Outreach Meetings Presentation - July to October 2016

Public Information Meeting - June 2016 (Ad)

BrochureComment Sheet, Presentation and Displays: 1 2 3 4 5 6

Project Numbers
State: 0638-029-156, P104, R204, C504
UPC: 5559
Federal: STP-5401 (691)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Feb. 19, 2019