Map of construction project districts

Recently Completed

Poland Road and Edgewater Street

Constructing a permanent roundabout in Loudoun County
Project Photos
Project at a Glance
Begin Date
February 2018

Est Completion Date
Substantial Completion: June 2018

Final Completion:
October 2018

Phase
Recently Completed

Cost
$1.9 million

Contractor
Arthur Construction

Locality
Loudoun

District
Northern Virginia

Contact
Michael Gleasman, P.E.
Construction

Note: This project was completed in October 2018.

About the Project

This project replaced the temporary marked and delineated roundabout at the intersection of Poland Road and Edgewater Street with a permanent single lane roundabout, including a raised center island, raised splitter islands, and curb/gutter along the approaches to improve safety at the intersection.

Schedule & Costs

Schedule

First Willingness Notice - June 2016
Second Willingness Notice - November 2016
Advertise for Construction – November 2017
Award Construction Contract - January 2018
Begin Construction - February 2018
"Pardon Our Dust" Meeting - March 2018
Substantial Completion - June 2018
Final Completion - October 2018

Estimated Costs

Preliminary Engineering: $480,000
Right of Way: $77,000
Construction: $1.3 million
Total: $1.9 million

Resources

Second Notice of Willingness  (November 2016)

First Notice of Willingness (June 2016)

Aerial of intersection

Programmatic Categorical Exclusion

Project Numbers

State: 0742-053-127, P101, R201, M501
UPC: 106942
Federal: HSIP-5A01 (701)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Oct. 23, 2018