Under Construction

Poland Road and Edgewater Street

Constructing a permanent roundabout in Loudoun County

Project Photos

Project at a Glance

Begin Date
February 2018

Est Completion Date
Substantial Completion: June 2018

Final Completion: Fall 2018

Phase
Substantial Completion

Cost
$1.9 million

Contractor
Arthur Construction

Locality
Loudoun

District
Northern Virginia

Contact
Raymond Kollack
Construction

Michael Gleasman, P.E.
Construction
703-259-1944

Note: The roundabout is complete with some final detail work continuing this summer without major traffic impacts.

About the Project

This project replaced the temporary marked and delineated roundabout at the intersection of Poland Road and Edgewater Street with a permanent single lane roundabout, including a raised center island, raised splitter islands, and curb/gutter along the approaches to improve safety at the intersection.

Schedule & Costs

Schedule

First Willingness Notice - June 2016
Second Willingness Notice - November 2016
Advertise for Construction – November 2017
Award Construction Contract - January 2018
Begin Construction - February 2018
"Pardon Our Dust" Meeting - March 2018
Substantial Completion - June 2018
Final Completion - Fall 2018

Estimated Costs

Preliminary Engineering: $480,000
Right of Way: $77,000
Construction: $1.3 million
Total: $1.9 million

Resources

Second Notice of Willingness  (November 2016)

First Notice of Willingness (June 2016)

Aerial of intersection

Programmatic Categorical Exclusion

Project Numbers

State: 0742-053-127, P101, R201, M501
UPC: 106942
Federal: HSIP-5A01 (701)