Recently Completed
Lucasville Road Drainage Improvements |
| Reconstruction and culvert replacement in Prince William County |
Project Photos
Project at a Glance
Summer 2012
Est Completion Date
November 2012
Cost
$3.24 million total (estimated)
Locality
Prince William
District
Northern Virginia
Contact
Chan Basnayake, P.E.
703-259-2947
Jeff Howard
703-366-1942
About the Project
This project reconstructed Lucasville Road (Route 692) near Hidden Spring Drive (Route 2559) in Prince William County.
The project raised the road’s profile and replaced an existing pipe culvert with a quadruple box culvert to improve drainage and mitigate flooding. The two-lane road was rebuilt with curb and gutter, and sidewalk was constructed on the east side of the road.
Lucasville Road was closed to through traffic during construction. See news release for details.
Estimated Cost
Engineering - $726,000
Right of way and utilities - $597,000
Construction - $1.92 million
Total - $3.24 million
Proposed Schedule
Public Hearing - Summer 2010
Right of way acquisition - Fall 2010
Advertise for construction - Late 2011/early 2012
Construction - Spring/summer 2012
Resources
Project brochure from public hearing held in August 2010
Environmental document (Categorical Exclusion)
UPC: 57416
State Project: 0692-076-334, P101, R201, M501, D651