Project at a Glance
Construction in March 2014 (Funding permitting)
Cost
Approx. $2.7 million
District
Northern Virginia
Contact
W. Calvin Britt, P.E.
703-259-2961
James C. Zeller, P.E.
703-259-3220
About the Project
This shared-use path along the west side of Berlin Turnpike (Route 287) will provide access to the Town Square. The project extends from the northern most corner of the Patriot Homes Development near Manor Drive north to Tilghman Drive. The section within the Town Square between Hammond Drive and West Broad Way will be developed by other entities.
VDOT is administering the project on behalf of the Town of Lovettsville, and it includes the asphalt shared-use path, curb and gutter within VDOT right of way, pavement markings and associated drainage improvements. The project will require grading and drainage easements and may be constructed in phases based on the availability of right of way, easements and/or funding.
This project is being financed with transportation enhancement funds.
Project Cost
Engineering of roadway plans - $530,000
Right of way acquisition and utility relocation (Phases 1 and 2) - $730,000
Construction (Phase 1 - north of the Town Center) - $830,000
Construction (Phase 2 - south of the Town Center) - $640,000
Total - Approximately $2.7 million
Project Schedule
Design hearing/comment period - April 2012
Design approval - September 2012
Right of way and utilities - March 2013
Construction (funding permitting) - March 2014
Resources
Project brochure (from the public hearing held April 11, 2012)