Lee Highway and Nutley Street |
| Intersection improvements in Fairfax County |
Project at a Glance
Estimated Summer 2013
Cost
Estimated $1.5 million
Locality
Fairfax
District
Northern Virginia
Contact
Jenny Ha
703-259-2907
About the Project
This project will make several improvements to the intersection of Lee Highway (Route 29) and Nutley Street (Route 243) in Fairfax County, including:
- Adding a second left-turn lane from eastbound Lee Highway to northbound Nutley Street
- Constructing a raised concrete median along Route 29 just east of Nutley to improve safety
- Upgrading the existing traffic signal equipment
No right of way, easements or utilities are expected to be required or relocated for this project.
Estimated Project Cost
Preliminary engineering: $315,000
Right of way: $200,000
Construction: $1 million
Total: $1.5 million
State Project: 0029-029-S56,P101,R201,M501 Fed. STP-5A01(211) UPC: 100648