In Design

I-66 Eastbound Connector Ramp to West Falls Church Metro Station

Constructing a connector ramp between two existing ramps in Fairfax County

Area Maps

Project at a Glance

Begin Date
Construction:
Summer 2019

Est Completion Date
Fall 2020

Phase
In Design

Cost
$4.8 million

Lengths and Limits
Quarter-mile west of Rt 7 to just east of Rt 7

Contractor
Lane Construction/
Rinker Design Associates

Locality
Fairfax

Contact
Mark Gibney, P.E., PMP
Construction
703-259-2734

About the Project

This project, part of the I-66 Inside the Beltway improvements, will provide direct access from eastbound I-66 to the West Falls Church Metro station by constructing a new ramp connection between two existing ramps (eastbound I-66 to Route 7 and the eastbound I-66 collector-distributor road adjacent to the station's parking garage.) 

Currently, vehicles on eastbound I-66 traveling to the West Falls Church Metro exit from I-66, turn right to head south on Route 7, turn left at the signalized intersection at Haycock Road, and then turn left onto Falls Church Drive. VDOT has identified operational and safety issues with this maneuver, especially during AM and PM peak periods.  

All improvements will be performed within existing VDOT right-of-way.

Schedule
Notice of Willingness to Hold Public Hearing - August 2017
Award Design-Build Contract: December 2017
Begin Construction: Summer 2019
Estimated Completion: Fall 2020

Estimated Costs
Preliminary Engineering: $300,000
Construction: $4.5 million
Total: $4.8 million

Resources

Notice of Willingness (August 2017)
Interchange Modification ReportFHWA Approval (August 2017)
Categorical Exclusion | Documentation of FHWA Review
Conceptual plan sheets: 1 | 2

Project Numbers
State: 0066-96A-493, P101, C501, B686
UPC: 110629
Federal: NHPP-066-1 (356)