Map of construction project districts

Under Construction

I-66 and Route 29

Repairs to the I-66 Exit 52 bridge in Centreville

Project Photos

Project at a Glance

Begin Date
May 29, 2014

Est Completion Date
Oct. 28, 2014

Cost
Approximately $2.1 million

Locality
Fairfax

District
Northern Virginia

Contact
Dinesh Singh, P.E.
Project Manager
703-259-2216
Chan B. Basnayake, P.E., PMP
Area Construction Engineer
703-259-2947

Construction Updates

(10/16/14) Deck overlay, joint reconstruction and repair of the bottom part of the bridge deck is complete. Spot coat of the bridge girders and approach road overlay is in progress. About 75% of the project is complete.

The project is expected to be completed on-time by Oct. 28, 2014.

About the Project

This project consists of repairs to both the I-66 eastbound and westbound bridges over Route 29 in Centreville (Exit 52).  Recent repairs to the steel beams and substructure were completed in 2012.  The deck overlay and joint reconstruction were not completed. The scope of this project is to complete the deck overlay, approach road overlay, and joint reconstruction.

The project's cost is approximately $2.1 million.

Construction began on May 29, 2014.  

Traffic Impacts

The work is being accomplished through nighttime lane closures on I-66. On Route 29, through lane and left-turn lane closures will be required to repair the bridge directly above the roadway.

Resources

Project Plans 1

Project Plans 2

Project Plans 3

 

UPC: 103924
State Project #: 0066-029-070, P102, P101, B619, B620

 

 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects