Map of construction project districts

In Design

Fraley Boulevard Widening

Brady's Hill Road to Route 234 in the Town of Dumfries/Prince William County

Area Maps

Project Photos

Project at a Glance

Phase
In Design

Cost
$130 million

Lengths and Limits
Bradys Hill Rd to Rt 234 (2 mi)

Locality
Prince William

District
Northern Virginia

Contact
Hong "Jenny" Ha, P.E.
Location & Design

Claudia Llana, P.E.
Preliminary Engineering

Note: A design public hearing will be held Thursday, Oct. 18 from 6:30 p.m. to 8:30 p.m. at Dumfries Elementary School, 3990 Cameron Street, Dumfries, VA 22026. A presentation will begin at 7 p.m.

About the Project

This project will widen about two miles of Fraley Boulevard (Route 1, primarily in the Town of Dumfries) to three lanes in each direction between Bradys Hill Road and Route 234 (Dumfries Road) in order to reduce congestion and improve safety and accessibility.

Currently in the Town of Dumfries, northbound Route 1 traffic is routed along the two-lane Fraley Boulevard and southbound Route 1 traffic is routed along Main Street. This project will add through lanes to Fraley Boulevard so it can be converted to three lanes of traffic in each direction with a raised median; as a result, Main Street will be converted to two-way local traffic via new pavement markings. The project will also:

  • Construct a shared-use path for bicyclists and pedestrians along the southbound side of the new Fraley Boulevard alignment, and a sidewalk along the northbound side.
  • Reconstruct and widen the Fraley Boulevard bridge over Quantico Creek to minimize flooding impacts and increase capacity.

Route 1 averages up to 28,000 vehicles a day within the project limits.

Schedule
Design Public Hearing - Oct. 18, 2018
Design Public Hearing Public Comment End - Nov. 1, 2018
Begin Construction - To be determined as additional funding sources are identified

Estimated Costs
Preliminary Engineering - $7 million
Right of Way Acquisition and Utility Relocation - $45 million
Construction - $78 million
Total - $130 million

The project’s preliminary engineering is financed with federal, state and Northern Virginia Transportation Authority (NVTA) funds. Also, the NVTA has provided additional funding anticipated for right of way acquisition and utility relocation. Additional funding sources are being identified for construction.

Resources

Design Public Hearing - Oct. 18, 2018 (Ad)

Project Plan Sheets: Bradys Hill Road to Graham Park Road | Graham Park Road to Possum Point Road | Possum Point Road to Route 234

Preliminary Right of Way Data Sheet

Title and Typical Section Sheets

Typical Section Graphic

Project Numbers
State: 0001-212-249, P101
UPC: 90339
Federal: STP-5A01 (228)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Oct. 11, 2018