Map of construction project districts

Under Construction

Fairfax County Parkway Interchange Improvements

Improving access from Rolling Road and northbound I-95

Area Maps

Click to view full-size map>

Project at a Glance

Begin Date
100391: March 2015
93033: TBD

Est Completion Date
100391: Spring 2016

100391: Under Construction
93033: In Design

$96.6 million (combined)

100391: American Infrastructure


Northern Virginia

Arif Rahman, P.E.
Project Manager (100391)
Andy Carper
Construction Manager (100391)
Shirlene Cleveland, P.E.
Program Manager for Design-Build Projects (100391)
Zamir Mirza
Project Manager (93033)
Terry Yates, P.E.
Preliminary Engineering Manager for Fairfax County (93033)

About the Project

This project will make interchange improvements at two locations—Fairfax County Parkway and Rolling Road, and Fairfax County Parkway and I-95—to help meet projected increases in future traffic demands.

Click here for a detailed map of the proposed improvements.

Proposed improvement: Widen the one-lane loop ramp to two lanes from north and southbound Rolling Road to Fairfax County Parkway north.

Alternative E was selected, which will eliminate the existing free flow right exit onto the loop by bringing the northbound right-turn lanes to a signalized intersection. This will address a safety conflict between traffic entering the loop from the northbound direction and traffic entering the loop from the southbound direction.

Proposed improvement: Construct a flyover ramp from northbound I-95 to northbound Fairfax County Parkway.

To allow traffic to continue to access northbound Backlick Road and the future interchange at Boudinot Drive, the project will eliminate the existing loop ramp and build left-turn lanes at the end of the ramp at Fairfax County Parkway and Loisdale Road.


Traffic demand on these ramps is expected to increase over the next 20 years due to the extension of the Fairfax County Parkway, regional population and employment growth, and the Base Realignment and Closure (BRAC) efforts to the Fort Belvoir North Area, located west of I-95 and east of the Fairfax County Parkway.

Daily forecasted volume on the ramp from northbound I-95 to westbound Fairfax County Parkway as well as the ramp connecting northbound and southbound Rolling Road to westbound Fairfax County Parkway is expected to increase.

The existing ramps cannot adequately handle the forecasted volumes. The proposed project will address specific traffic deficiencies at the interchanges, namely the relatively low capacity of the one-lane loop ramps, to accommodate the increases.

Schedule and Cost

The total cost of both projects combined is currently estimated at $96.6 million, including $8.7 million for preliminary engineering, $10.6 million for right of way and $77.3 million for construction. 

Construction on the Rolling Road loop ramp (UPC: 100391, State Project # 0286-029-947) began in March 2015. Construction is scheduled to be completed in the spring of 2016. The total cost of the project is currently estimated at $14 million, including approximately $600,000 for preliminary engineering, $600,000 for right of way and $12.8 million for construction.

The I-95 flyover ramp (UPC: 93033, State Project # 0095-029-846) is currently under preliminary design up to the public hearing phase only.  It is not funded for right of way or construction.  The project advertisement date is to be determined based upon availability of funding. The total cost of the project is currently estimated at $82.6 million, including $8.1 million for preliminary engineering, $10 million for right of way and $64.5 million for construction. 

Environmental Impacts

An environmental assessment was prepared and approved by the Federal Highway Administration for this project, and includes a full listing of considered impacts and additional findings from the environmental evaluation.

Draft Environmental Assessment
Revised Environmental Assessment
Finding of No Significant Impact
Final Noise Analysis and Final Air Quality Analysis
Archaeology Summary


Fairfax County Parkway and Rolling Road:

Improvements to the Fairfax County Parkway/Rolling Road Interchange

State Project: BRAC-96A-101,P101,N501 Federal Project: NH-000S(218) UPC: 81738

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Aug. 31, 2015