Recently Completed
Atlantic Boulevard Extension |
| From Church Road to Magnolia Road in Loudoun County |
Project at a Glance
Fall 2010
Est Completion Date
Late 2011
Open to Traffic
Spring 2012
Final completion
Cost
$24 million
Lengths and Limits
0.4 miles
Contractor
Route 28 Corridor Improvements, LLC
Locality
Loudoun
Contact
Susan Shaw
Design/Build Manager
703-259-2232
Bill Atkins
Construction Manager
703-259-2939
About the Project
This project extended Atlantic Boulevard from Church Road to Magnolia Road. The new section of road, almost a half-mile long, completed Atlantic Boulevard, providing a continuous road parallel to Route 28 from Sterling Road (Route 846) north to Route 7.
The project features four lanes, a raised median, an asphalt multi-purpose trail on the east, a concrete sidewalk on the west, and a single-span bridge over the Washington and Old Dominion (W&OD) Trail with connections to the trail.
Although it was constructed under the Route 28 PPTA design-build contract, the extension was state-funded and will be maintained by VDOT. The project opened to traffic in late 2011, with final completion in spring 2012.
The total cost, including preliminary engineering, right of way, utilities and construction was $24 million.