Map of construction project districts

Under Construction

Aden Road Bridge Repair and Expansion

Over the Norfolk Southern Railroad in Prince William County
Project Photos
Project at a Glance
Begin Date
December 2015

Est Completion Date
New Bridge Opening:
December 2016

Truss Bridge Reopening: March 2019

Final Completion:
Late Spring 2019

Cost
$8.3 million

Contractor
Allan Myers VA

Locality
Prince William

District
Northern Virginia

Contact
Richard Gutridge
Construction

Michael Gleasman, P.E.
Construction

Note: The historic truss bridge reopened to northbound traffic and the recently constructed bridge reopened to southbound traffic March 14.

About the Project

This project rehabiliated the historic wrought-iron truss bridge that carries northbound Aden Road (Route 646) over the Norfolk Southern Railroad and constructed a new parallel bridge for southbound traffic to enable two-way traffic over the railroad. The project also made intersection improvements, including a new median, at Marsteller Drive.

Built in 1882 for the Keystone Bridge Company, the truss bridge was purchased in the early 1900s and moved to Aden Road by Norfolk Southern, who transferred ownership to VDOT in 2014. In March 2014, the weight limit on the one-lane truss bridge was reduced from six tons to four. The bridge was closed in May 2015 due to deterioration revealed in inspections, and was removed from the railroad crossing in January 2016. The new one-lane bridge opened to traffic in December 2016.

VDOT originally planned to repair the truss bridge and reopen it for northbound use, however, upon removal, the bridge showed substantial structural deficiencies. A revised plan/design was developed with the Virginia Department of Historic Resources and the community that allows the truss bridge to remain on the National Register of Historic Places.

Construction resumed in July 2018 to implement the revised plan/design; the new Aden Road bridge was temporarily closed to facilitate the truss bridge reinstallation and rehabilitation.The truss bridge was put back in place over the railroad in November 2018 and reopened to traffic along with the new bridge in March 2019. The project is scheduled for final completion in spring 2019. 

Aden Road averages 3,500 vehicles a day at the railroad crossing.

Schedule
Public Information Meeting - December 2011
Design Public Hearing - September 2013
Begin Construction - December 2015
Truss Bridge Removal - January 2016
New Bridge Open to Traffic - December 2016
New Bridge Temporarily Closed - July 2018
Truss Bridge Reinstalled - November 2018
Truss Bridge and New Bridge Reopening - March 2019
Final Completion - Late Spring 2019

Estimated Costs
Preliminary Engineering - $1.2 million
Right of Way Acquisition and Utility Relocation - $339,000
Construction - $6.7 million
Total - $8.3 million

This project is financed with federal, state and Prince William County funding. Norfolk Southern donated a construction easement to allow the work to be completed.

Resources

Design Public Hearing - September 2013

Presentation and East-West View Display

Memorandum of Agreement - May 2013

Preferred Option Presentation - May 2013

Preliminary Options Presentation - January 2013

Public Information Meeting - December 2011

An information meeting was held to present preliminary plans to improve safety and add capacity for the structurally deficient bridge, and to receive comments and suggestions on this historically significant bridge and impacts to the surrounding area.

Project Numbers
State: 0646-076-971, P101, R201, C501, B649, B654
UPC: 90519
Federal: BR-5401 (924), STP-5A01 (476), STP-5A01 (614)

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: March 28, 2019