This project will rehabilitate the northbound Route 29 (Lee Highway) bridge over Cub Run. The bridge was built in 1954.

The planned improvements include:

  • Replacing the concrete deck
  • Installing steel beams
  • Rebuilding the concrete pedestals
  • Replacing the bridge bearings
  • Repairing cracks

The bridge averages 13,000 vehicles a day; Route 29 averages 26,000 combined northbound and southbound vehicles a day at Cub Run.

Estimated Costs
Preliminary Engineering - $230,000
Construction - $3 million
Total - $3.2 million

The project is being financed with state and federal State of Good Repair funds used for maintenance of structures and bridges.

Benefits 

This project aims to improve safety and extend the overall life of the bridge.

Major Milestones 

Public Information Meeting - November 2019
Begin Construction - Summer 2020
Final Completion - Summer 2021

Resources

Contact Info:

Edwin Woo, P.E.
Structure & Bridge

Andrew Beacher, P.E.
Preliminary Engineering

Other relevant links:

Programmatic Categorical Exclusion - April 2019

Previous Meetings >>

Major funding source: State of Good Repair

Phase: In Design

UPC: 112361

State ID: 0029-029-403, P101

Federal ID: STP-BR09 (297)

Lat/Long: 38.833228, -77.463170

Locality: Fairfax