Map of construction project districts

Coming Soon

Route 35 Darden Bridge Replacement

Project at a Glance

Begin Date
Est. Construction Begin: January 2015

Est Completion Date
November 30, 2015

Cost
Est. $9,476,000

Lengths and Limits
From 0.072 miles west of Southampton County Line to 0.364 miles west of Southampton County Line

Contractor
Waterfront Marine Construction

District
Hampton Roads

Contact
Ron Rouse, Waterfront Marine Project Manager
757-646-5010
Hampton Roads Communications
757-925-1660

Project Description

The Rte 35 (Hancock) Bridge is currently a two lane bridge with an average volume of approximately 3,400 vehicles per day. By the year 2036, the traffic volume is projected to increase to approximately 4,525 vehicles per day. The proposed improvements to the bridge will make significant safety improvements to the area.

The project consists of replacing the existing two lane steel truss bridge with a two lane structure with shoulders, grading, paving and drainage on the two lane asphalt approaches. The current bridge was constructed in 1929 and is structurally deficient and weight restricted.

The new bridge will have the following features:
Widened roadways: 12’ lanes with 8’ shoulders
Bridge Clearance of 26’ above mean high water
Bridge length of approximately 900’ with approaches of approximately 400’ in each direction

 

Project Update

A design/location public hearing was held on Feb. 7, 2013. The contract for the design and construction of the project was awarded to Waterfront Marine Construction on Oct. 17, 2013, at an estimated construction cost of $9.4 million. 

The project is in the final stages of the design phase and final plans are near completion. Waterfront Marine and the Design Contractor URS have acquired the required Right of Way and are currently working on acquiring required permits for construction. The current plan is to start construction work and close the bridge in early January. All work will begin upon closing the bridge to traffic.

F.A.Q.

Will the bridge remain open during construction?
No.  Waterfront Marine Inc., has scheduled a 300-day bridge closure during which the old bridge will be dismantled and the new bridge constructed in its place. The bridge will be closed in both directions during this fixed, 300-day period. The contract states that the bridge must be open to traffic in both directions at the final roadway configuration once that 300-period is complete.

When will the bridge be closed?
The contractor currently estimates the bridge closure will start January 5, 2015. The 300-day bridge closure will last until October 31, 2015. At that time the bridge will be opened to the final roadway configuration. Additional work may take place in the area without requiring any lane closures until the project's final projected completion date on November 30, 2015.

How can we reach the Town of Courtland during the bridge closure?
There is a seven-mile detour planned via Route 58 & Business Route 58. Detour signs will be in place to direct traffic through the detour and access the Town of Courtland from Route 58 onto Business Route 58 (Jerusalem Rd and Main St) into the Town of Courtland. The Town of Courtland businesses will remain open and accessible throughout the duration of the project and bridge closure.

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Oct. 29, 2014