Map of construction project districts

Under Construction

George Washington Memorial Highway Widening Project (Route 17)

York County

Project Photos

Project at a Glance

Begin Date
August 2013

Est Completion Date
Winter 2016

Cost
Estimated Cost: $25.2 million

Contractor
E.V. Williams

Locality
York

District
Hampton Roads

Contact
Hampton Roads Public Affairs
757-925-2583

Project Overview

George Washington Memorial Highway (Route 17) in York County is a four-lane divided highway with an average daily traffic volume of approximately 56,000 vehicles. There is frequent traffic congestion and delays during peak travel periods. Motorists are experiencing traffic congestion with delays during the commuter peak travel periods. Traffic volume is projected to increase to about 90,000 vehicles per day by the design year 2035. 

The proposed improvements will increase the capacity of George Washington Memorial Highway between Hampton Highway and Wolf Trap Road, from four lanes to six lanes, with three lanes in each direction. The proposed roadway will include a raised median, curb and gutter, with a shared-use path parallel to the northbound lane from Mill Road to Showalter Road. The two existing bridges over the Poquoson River will be replaced with one bridge carrying six lanes of traffic and a shared-use path. 

The project has been included in the FY2012-2017 Six-Year Improvement Program. Planning, engineering, and right-of-way acquisition are complete.

Current Status: Work in Phase I continues with construction of the new bridge. Pile driving, concrete form work and pours have been completed and the beams have been set. The deck pour will begin later this month and is expected to be completed by late August. Permanent storm drainage systems and mainline water mains have been installed. Widening activities in the north- and southbound lanes are nearly complete, and curb and gutter installation remains ongoing. Traffic signal poles and mast arms were recently installed at the intersection of Ella Taylor Road, Heritage Square, Oriana Road/Lakeside Drive and George Washington Shopping Center. 

In Phase II, waterline installation continues, in addition to relocation of water services, installation of storm sewer pipes and drainage structures and widening of the outside lanes from Lakeside Drive/Oriana Road to George Washington Shopping Center. Preparations are underway to begin installation of underground signal work, conduit, junction boxes and signal cabinets.

Temporary traffic signal work and storm sewer pipe installation will soon begin in Phase III. 

On Thursday, Jan. 22, an update on the project was presented at Grafton High School in York County: 

George Washington Highway Widening Project Presentation

Project Updates:
To receive email project updates, send a request to hamptonroadspublicinfo@VDOT.virginia.gov with "Subscribe to George Washington Highway Project Updates" in the subject line.

Follow us on Twitter and Facebook for project updates.

More project photos are available on Flickr.

Traffic Alerts

Throughout the duration of the project, weeknight single-lane closures are in effect from 7 p.m. until 5 a.m. Depending upon the work activities, lane closures may occur during the daytime hours from 9 a.m. to 3 p.m.and on weekends if necessary. 

Showalter Road traffic is being detoured to Ella Taylor Road through late fall 2015. 

Traffic pattern changes:

Southbound traffic is being shifted slightly to the right from Sports Way to Ella Taylor Road to allow construction crews access to perform work in the median. Slight roadway modifications and a new traffic pattern are also in effect on the signalized side streets.

Northbound traffic has been shifted to the right outside lanes from the Magruder Boulevard ramp to north of Mill Road to allow construction crews access to perform work in the median. 

Other Project News

New Traffic Detection System Installed
Wireless sensors (also known as pucks) have been installed in the roadway along the Route 17 George Washington Highway project corridor. The sensors detect vehicles and transmit data for analysis of traffic speed, travel times and volume trends. Learn more about pucks here: Traffic Systems Face Off with Game Changing Technology

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: July 31, 2015