Map of construction project districts

Under Construction

George Washington Memorial Highway Widening Project (Route 17)

York County

Project Photos

Project at a Glance

Begin Date
August 2013

Est Completion Date
Winter 2016

Cost
Estimated Cost: $25.2 million

Contractor
E.V. Williams

Locality
York

District
Hampton Roads

Contact
Hampton Roads Public Affairs
757-925-2583

Project Overview

George Washington Memorial Highway (Route 17) in York County is a four-lane divided highway with an average daily traffic volume of approximately 56,000 vehicles. There is frequent traffic congestion and delays during peak travel periods. Motorists are experiencing traffic congestion with delays during the commuter peak travel periods. Traffic volume is projected to increase to about 90,000 vehicles per day by the design year 2035. 

The proposed improvements will increase the capacity of George Washington Memorial Highway between Hampton Highway and Wolf Trap Road, from four lanes to six lanes, with three lanes in each direction. The proposed roadway will include a raised median, curb and gutter, with a shared-use path parallel to the northbound lane from Mill Road to Showalter Road. The two existing bridges over the Poquoson River will be replaced with one bridge carrying six lanes of traffic and a shared-use path. 

The project has been included in the FY2012-2017 Six-Year Improvement Program. Planning, engineering, and right-of-way acquisition are complete.

Current Status: Work in Phase I continues with construction of the northbound section of the bridge, including the approaches. Other work includes curb and gutter installation, ongoing installation of the permanent storm drainage systems, widening and reconstruction of the northbound and southbound lanes, and continued installation of the water line. The sound wall, storm water management basin, and the southbound section of the bridge are now complete.  

In Phase II, traffic has shifted to the median. Crews also restriped the temporary lane markings that had worn away as a result of the snow events and plowing operations. In Phase III, temporary widening of the median continues, as well as mobilization for utilities. Additional activities for Phases II and III include the installations of erosion and sediment controls, the water main and hydrants, and storm drain and utilities.

Signalization activities, such as pole foundations, setting poles and installation of conduit are ongoing throughout the project. 

On Thursday, Jan. 22, an update on the project was presented at Grafton High School in York County: 

George Washington Highway Widening Project Presentation

Project Updates:
To receive email project updates, send a request to hamptonroadspublicinfo@VDOT.virginia.gov with "Subscribe to George Washington Highway Project Updates" in the subject line.

Follow us on Twitter and Facebook for project updates.

More project photos are available on Flickr.

Other Project News

New Traffic Detection System Installed
Wireless sensors (also known as pucks) have been installed in the roadway along the Route 17 George Washington Highway project corridor. The sensors detect vehicles and transmit data for analysis of traffic speed, travel times and volume trends. Learn more about pucks here: Traffic Systems Face Off with Game Changing Technology

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: March 24, 2015