Map of construction project districts

In Design

Berkley Bridge Rehabilitation

Norfolk

Project at a Glance

Begin Date
Design Start: 2012

Est Completion Date
Design Completion: 2016

Contact
Public Affairs
757-925-1647

About the Project

This project will replace all the electrical, mechanical, and control components of the drive systems of this movable bridge.

Current Status

The design consultant was given notice to proceed on November 30, 2012. A preliminary design report was submitted in April 2013 and was reviewed by VDOT. The project is currently in the final design phase, anticipated to be complete in Spring 2016. Currently, there is no funding allocated for construction of this project.

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Jan. 5, 2015