Map of construction project districts

Under Construction

Route 639 (Ladysmith Road)

Turn Lanes at Route 1 Intersection

Project at a Glance

Begin Date
January 2014

Est Completion Date
May 2015

Cost
$2.8 million

Contractor
J.L. Kent & Sons, Inc.

Locality
Caroline

Contact
Daniel Harrison, VDOT Project Manager
540-899-4288
Kelly Hannon, VDOT Communications Manager
540-374-3344

Project Details

The Virginia Department of Transportation plans to enhance safety and add vehicle capacity by building left turn lanes on Route 639 (Ladysmith Road) from the intersection of Route 1 to 0.35 miles east of Route 1 in Caroline County. 

All road widening to accommodate the new turn lanes will be on the northern side of Route 639, with right turn lanes being replaced at the existing entrance of Wright's Chapel Church, Center Drive, and the adjacent shopping center. 

Construction will occur on the south side of Route 639 primarily for the increased shoulder width and stormwater management requirements. 

Left turns from eastbound Route 639 will be accommodated with a universal left turn lane. This approach will allow left turns from westbound Route 639 should the land to the south become developed. 

 

Public Hearing

A public hearing on the project was held on Thursday, Oct. 27, 2011 from 4-7 p.m. at Madison Elementary School in Caroline County. 

Click Here to view the public hearing brochure. 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Jan. 10, 2014