Proposed
Route 633 (Bull Church Road) Bridge Replacement at South River |
| Caroline |
Project at a Glance
Construction Estimated to Begin in Spring 2014
Est Completion Date
Construction Estimated to End in Spring 2015
Cost
$1.3 million
Locality
Caroline
Contact
Kevin Northridge, Project Manager
540-899-4288
Kelly Hannon, Communications Manager
540-374-3344
Project Overview
The Virginia Department of Transportation (VDOT) has proposed replacing the bridge at the South River on Route 633 (Bull Church Road) in Caroline County.
The existing bridge is structurally deficient, and was built in 1935.
The project is currently estimated to cost $1.3 million. VDOT anticipates advertising the proposed project for construction in February 2014, with construction beginning in spring of 2014. The bridge replacement would take approximately one year to complete.
Traffic on Bull Church Road would not be able to pass at the bridge during construction, since it is a complete bridge replacement. There will be a detour while construction is underway.
The new bridge will have the same number of travel lanes as the existing bridge, but would have wider travel lanes and new railing.
Project Documents
VDOT held a public hearing on this proposed project on Wednesday, April 25, 2012. The meeting was held from 4-7 p.m. at Madison Elementary School in Caroline County.
Documents from the meeting are available online: