Map of construction project districts

Recently Completed

Route 610 (Garrisonville Road) Bridge Rehabilitation at Aquia Creek

Stafford County

Project at a Glance

Begin Date
April 2012

Est Completion Date
August 30, 2012

Cost
Estimated Total Cost: $434,777

Contractor
McClain & Co, Inc.

Locality
Stafford

Contact
Steve Wilson, Construction Manager
540-899-4288
Kelly Hannon, Communications Manager
540-374-3344

Project Details

Rehabilitation has begun to repair the bridge on Route 610 (Garrisonville Road) in Stafford County at Aquia Creek, located west of the intersection with Joshua Road.

Daytime, temporary single-lane closures will be required initially as workers replace guardrail along the bridge, and reconstruct the shoulders. Motorists should be alert for flagging crews at the bridge directing traffic.

In May, temporary traffic signals will be installed on both ends of the bridge. The signals will remain until the project is completed in August 2012.

One lane of the bridge will be closed during this construction phase. Eastbound and westbound traffic will be required to alternate crossing the bridge in a single travel lane.

This project will replace the bridge joints, and repair the surface of the bridge substructure and superstructure.

The project completion date is Aug. 30, 2012.

Cost and Contractor

The project’s total cost is estimated to be $434,777. A contract for $311,018 was awarded to McClain & Co, Inc.