Map of construction project districts

Under Construction

Fall Hill Avenue Widening and I-95 Bridge Replacement

City of Fredericksburg

Project Photos

Project at a Glance

Begin Date
Construction began in February 2015

Est Completion Date
April 20, 2017

Phase
Construction

Cost
Estimated cost $44.4 million

Contractor
Design-Build Team: Whitman, Requardt & Associates and Corman Construction

Locality
Fredericksburg

District
Fredericksburg

Contact
Michael Coffey, VDOT Area Construction Engineer
(540) 899-4288
Kelly Hannon, VDOT Communications Manager
(540) 374-3344

About the Project

The Virginia Department of Transportation is widening Fall Hill Avenue from two lanes to four lanes with a raised median from Carl D. Silver Parkway (Central Park) to a roundabout just west of the bridge over the Rappahannock Canal.

Mary Washington Boulevard will be extended from the Mary Washington Hospital campus at Hospital Drive to intersect at the new roundabout, which will provide a new connection between Route 1 (Jefferson Davis Highway) and Fall Hill Avenue.

Fall Hill Avenue carries approximately 17,200 vehicles per day, and the number of vehicles is expected to double in the next 20 years.

Fall Hill Avenue will remain open to traffic during the project, with periodic lane closures during off-peak hours. 

Project Fact Sheet

Construction Update: January 2017

The project contractor has submitted a revised schedule with a new project completion date of April 20, 2017.

Widening work is continuing along Fall Hill Avenue and Mary Washington Boulevard.

Additional construction activites include:

  • Final paving
  • Final sign installation and pavement markings
  • Final overpass work and inspection
  • Finishing construction of a roundabout at the intersection of Fall Hill Avenue and Mary Washington Boulevard, immediately west of the Rappahannock Canal Bridge
  • Construction of a replacement basketball court, baseball field, playground and field parking area

Motorists should stay alert for work crews, barrels, equipment, and traffic shifts in the work zone.

The contractor has been working six days a week with multiple work crews to complete the project as quickly as possible, but some of the final activities, such as paving and painting pavement markings, are weather and temperature dependent.

VDOT and the contractor regret the inconvenience a delay brings, and we are working to complete this project as quickly as possible.

VDOT will communicate updates this winter and spring as work progresses. Updates will be posted to www.VirginiaDOT.org on this project page, VDOT social media platforms, and through news releases posted in our newsroom.

Specific lane closures are advertised each week in Hot Spots, a weekly lane closure list for VDOT's Fredericksburg District.

Traffic Pattern Changes on Mary Washington Boulevard

Traffic is anticipated to significantly increase on Mary Washington Boulevard when the project is complete, due to the new direct connection between Fall Hill Avenue and Route 1.

Due to the increased amount of traffic, several left turn movements are no longer permitted along Mary Washington Boulevard. These are permanent traffic pattern changes that will remain in place once construction is complete.

CVS Pharmacy

The CVS pharmacy parking lot access will remain open to right turns in and right turns out only on Mary Washington Boulevard. Left turns into the pharmacy parking lot are no longer permitted.

Motorists seeking to access the CVS pharmacy parking lot may make a U-turn at the intersection of Route 1 and Mary Washington Boulevard. The project design has allowed space for U-turns to be made at the Route 1 and Mary Washington Boulevard intersection.

Sam Perry Boulevard and Mary Washington Boulevard

Left turns are no longer permitted from Sam Perry Boulevard to proceed north on Mary Washington Boulevard in the direction of the Mary Washington Hospital emergency room and Fall Hill Avenue.

Project Documents

“Pardon Our Dust” Meeting  

VDOT held a "Pardon Our Dust" public meeting from 5-7 p.m. on December 2, 2014 at James Monroe High School to share information about the upcoming construction project. 

Meeting Brochure

Meeting Presentation

Map 1

Map 2

Construction Sequence and Phases

Project Milestones 

 

 

 

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Jan. 10, 2017