Map of construction project districts

Under Construction

Route 688 (Leeds Manor Road), Fauquier County

Replacement of bridge over Thumb Run

Project at a Glance

Begin Date
Late summer 2015

Est Completion Date
July 21, 2016

Phase
Under construction

Cost
$1.96 million construction contract

Lengths and Limits
0.059 mile; from 0.035 mile south to 0.034 mile north of Thumb Run

Contractor
Martins Construction Corp. of Falls Church

Locality
Fauquier

District
Culpeper

Contact
Wade Smith
540-738-6261

Construction Update

Beginning Thursday, Jan. 14, traffic will be restricted to one lane controlled by temporary signals at the Route 688 bridge over Thumb Run.

(The traffic pattern change was originally scheduled for Dec. 10 but was postponed due to a problem with timing of the temporary traffic signals.)

Temporary signals and other traffic-control devices will be installed to accommodate construction. The contractor will work in phases to maintain a single travel lane throughout construction, working first on the southbound half of the bridge.

Motorists should remain alert for new signs and traffic controls as well as workers and equipment near the travel lanes.
 

Project Purpose

The primary purpose of this project is to replace the substandard Route 688 (Leeds Manor Road) bridge over Thumb Run in Fauquier County. The existing concrete-slab bridge was built in 1925.
 

What Is Proposed?

VDOT proposes to construct a new two-lane, prestressed concrete slab bridge in place of the existing bridge. The proposed bridge will be 54 feet long and 26 feet wide.

Located approximately 350 feet south of the bridge, an additional structure that spans the tributary of Thumb Run is proposed to be replaced with a new 20 by 47 ft. concrete box culvert.

Based on comments received at the 2013 public hearings, the bridge replacement will be done in phases with a single travel lane maintained throughout construction. A signal will control two-way traffic through the work zone.

Construction began in late summer 2015, with a July 2016 completion date.

Approximately 580 vehicles use Route 688 daily, according to a 2011 traffic count.
 

Project Costs

Total cost: $2,710,038

Engineering of Roadway Plans: $650,000
Right of Way Acquisition and Utility Relocation: $63,511
Construction: $1,996,527


 

Project Schedule

Public hearing: November 19, 2013
Public comment period ends: November 29, 2013
Right of way acquisition and utility relocation: Winter 2013
Construction advertisement: Winter 2014
Construction completion: July 21, 2016

The project's schedule is subject to change.
 

Resources

Temporary Signals Activate Thursday, Dec. 10 at Route 688 Bridge
News release, December 7, 2015

Materials from the Nov. 19, 2013, public hearing:
   Public hearing brochure Adobe Acrobat PDF (100 KB)
   Public hearing comment sheet Adobe Acrobat PDF (83 KB)

News release: Rt. 688 Bridge Project Subject of March 26 Hearing

Materials from the March 26, 2013, public hearing:
   Public hearing brochure Adobe Acrobat PDF (100 KB)
   Public hearing comment sheet Adobe Acrobat PDF (83 KB)