Map of construction project districts

Recently Completed

Route 672, Culpeper County

Superstructure replacement, bridge over Mountain Run

Project at a Glance

Begin Date
March 3, 2008

Est Completion Date
July 31, 2008

Contractor
General Excavation, Inc.

Locality
Culpeper

District
Culpeper

Contact

Culpeper Public Affairs
800-367-7623

Project Completed On Time, On Budget

The project was finished on June 20, 2008, 41 days ahead of the July 31 scheduled completion date. The final cost was $416,499.19, which was $19,079.43 under the $435,578.62 contract budget.

Project Information

What's being done?
Replacing the existing superstructure of the bridge over Mountain Run on Route 672 in Culpeper County. 

Benefits
The bridge deck will be widened which will improve traffic flow.

Features
The steel beams/wooden deck will be removed and replaced by pre-stressed concrete beams with surface asphalt.

Impact on Traffic
The roadway will be closed during construction.  Traffic will be detoured. Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects

Page last modified: Oct. 14, 2012