Route 655, Fauquier Co.

Replacement of the bridge over Tinpot Run

Project at a Glance

Begin Date
March 2013

Est Completion Date
Nov. 11, 2013

Recently Completed

$2,313,177.80 construction contract

Lengths and Limits
0.5 mile; from 0.4 mile west of Route 1201 to 0.1 mile east of Route 1201

General Excavation Inc.



Office of Communications

On Nov. 11, 2013, VDOT completed the replacement of the Route 655 (Tinpot Run Lane) bridge over Tinpot Run, located just east of the town of Remington. The existing steel-beam, timber-deck bridge was built in 1960 and was posted with a 13-ton weight limit.

With this project, VDOT demolished the old bridge and constructed a new bridge of pre-stressed concrete beams with 10-foot-wide travel lanes and a 10-foot-wide shared-use path for bicyclists and pedestrians on the north side. Curb and gutter were added to Route 655 through the project limits.

The project also realigned the intersection of Route 655 and Route 1201 to improve safety.

This section of Route 655 carries approximately 1,100 vehicles per day.

News Releases and Project Information

News release: Rt. 655 in Fauquier Co. to Close Completely June 10
May 30, 2013

Route 655 Bridge Replacement Subject of Public Hearing (32 KB)
July 19, 2010

Public hearing brochure (305 KB)