Route 250 Bypass Interchange at McIntire Road

Administered by the City of Charlottesville

Project at a Glance

Begin Date
March 2013

Est Completion Date
Opened to traffic Feb. 5, 2015; contract completion July 2, 2015

Phase
Under Construction

Cost
$20.1 million construction contract

Contractor
General Excavation Inc. of Warrenton

Locality
Charlottesville

District
Culpeper

Contact
Jeanette Janiczek, City of Charlottesville
434-970-3309
David Cubbage, VDOT Urban Program Project Manager
540-829-7554

Route 250 Bypass logo






The City of Charlottesville is constructing a multi-modal roadway project to replace the at-grade intersection of the Route 250 Bypass and McIntire Road. The diamond-shaped, grade-separated interchange includes a connection to the southern leg of the John W. Warner Parkway. The new interchange will include shared-use paths, sidewalks and bike lanes.

The project schedule is as follows:

Project Advertised:  November 11, 2012

Bids Received:  January 8, 2013

Work Commenced:  March 4, 2013

Opened to Traffic: February 5, 2014

Fixed Final Completion Date:  July 2, 2015

Click on the project logo for additional information.
 

For More Information

This project is locally administered through the City of Charlottesville's Department of Neighborhood Development Services. Links and data shown are for informational purposes only. All inquiries, document submittals and communication on the project must be directed to Jeanette Janiczek, 434-970-3309.

Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects
Page last modified: Feb. 18, 2015