Route 15/29 Business improvement project in Culpeper

Widening from two to four lanes

Project at a Glance

Begin Date
March 2008

Est Completion Date
November 30, 2009

Cost
$11,423,000

Lengths and Limits
From 0.10 mile south of N.C.L. of Culpeper to the intersection of Route 666.

Contractor
Tavares Concrete Co., Lorton, Va.

Locality
Culpeper

District
Culpeper

Contact

Culpeper Public Affairs
800-367-7623

Construction was completed on Nov. 17, 2009, 13 days ahead of the scheduled completion date. The project was $165,105 under the contract cost upon completion. 

 

About the Project

What's being done?
This project will widen Route 15 (James Madison Highway) from two lanes to four lanes from 0.10 mi. south of the north corporate limits of the Town of Culpeper to the intersection with Route 666.

Benefits
Traffic flow improvement and safer intersections. 

Features
This project will add two additional lanes with sidewalk, curb and gutter and upgrade intersections.

Impact on Traffic
Traffic will be reduced to one lane as needed through the project and will be controlled by flaggers. Bristol area projects Salem area projects Staunton area projects Lynchburg area projects Culpeper area projects Richmond area projects Northern Virginia projects Fredericksburg area projects Hampton Roads projects