Moccasin Gap Bypass in Scott County - Phases II and III |
Project at a Glance
What's Being Done
Right of way acquisition is currently underway for Phases II and III of the Moccasin Gap Bypass in Scott County. The cost for right of way is approximately $7.3 million. Roadway grading work for Phases II and III is scheduled to begin in fall 2010.
Phase II
- includes all of the gradework for the Moccasin Gap Bypass.
- Estimate for gradework: $26 million.
- The project will be advertised in July 2010.
- Gradework should begin in fall 2010.
Phase III
- includes the bridges and the pavement for the entire
project.
- Currently, Phase III funds have not been identified in the Six-Year Improvement Plan.
Contacts
James Parsons, P.E., (276) 346-1911Page last modified: July 29, 2008