Recently Completed
Interstate 81 bridges over Scratch Gravel in Marion |
| Bridge reconstruction project |
Project at a Glance
Begin Date
mid-October 2011
Est Completion Date
August 2012 (finished July 2012)
Contractor
DLB, Inc., Hillsville
Locality
Smyth
mid-October 2011
Est Completion Date
August 2012 (finished July 2012)
Contractor
DLB, Inc., Hillsville
Locality
Smyth
Contact
What's being done?
Repairs to the Interstate 81 bridges over Scratch Gravel Road near Exit 45 in Marion were completed in July 2012. The contractor for the project, DLB, Inc., Hillsville, completed the project on time and within budget.
Page last modified: Feb. 7, 2013