I-95 NORTHBOUND BRIDGE REPLACEMENT OVER ROBIN HOOD ROAD TO BEGIN MONDAY NIGHT
Robin Hood Road and Hermitage Road ramps closed during replacements

COLONIAL HEIGHTS — This week, the Sherwood Avenue bridge became the seventh of 11 bridges to be replaced as part of the I-95 Richmond Bridge Restorations project. Crews will begin replacement of the I-95 northbound bridge over Robin Hood Road Monday night, weather permitting. This bridge will require the placement of 12 pre-cast bridge units and is expected to continue weeknights through the remainder of the month. The I-95 southbound bridge over Robin Hood Road was replaced November 2012. The project is currently on schedule for completion in June 2014.

Weeknights from 8 p.m. to 6 a.m., I-95 will be reduced to one travel lane in each direction between Boulevard (mile marker 78) and Belvidere Street (mile marker 76). Expect major delays. In addition, traffic on Robin Hood Road under I-95 will be reduced to one lane in each direction.

In addition, weeknights from 7 p.m. to 6 a.m., the following will be closed to facilitate Robin Hood Road northbound bridge replacement activities. Drivers are encouraged to use the posted detour.

  • The ramp from Robin Hood Road to I-95 south
  • The ramp from I-95 north to Hermitage Road (exit 78)
  • Overbrook Road under I-95
  • Sherwood Avenue under I-95

Just south of the bridge over Robin Hood Road, I-95 north traffic will merge onto the southbound bridge. Both I-95 north and south traffic will use the southbound bridge to maneuver around the construction. VDOT strongly encourages I-95 and I-64 travelers through Richmond use one of the following alternate routes to bypass the construction.

From I-95 south (Henrico): Access I-295 at exit 84 to reach I-64 east/west or areas south of Richmond; through travelers can use I-295 south to bypass Richmond and re-enter I-95 south at exit 46 in Prince George County. Local traffic can also take exit 82 (Chamberlayne Avenue/Route 1/301 south) to reach Richmond destinations.

From I-95 north (Prince George): Access I-295 at exit 46 to reach I-64 east/west or areas north of Richmond; through travelers can use I-295 north to bypass Richmond and re-enter I-95 north at exit 84 in Henrico County. 

From I-64 east (Goochland/Henrico): There are three alternate routes:

  • Access Route 288 south at exit 175 in Goochland to reach Chesterfield County locations and to re-enter I-95 at exit 62
  • Access I-295 at exit 177 to reach I-95 north or I-64 east of Richmond
  • Access I-195 south at exit 186 in Richmond to reach downtown destinations, Route 76/Powhite Parkway Extension (toll) through Chesterfield County or the Downtown Expressway (toll).

From I-64 west (Henrico/New Kent): Access I-295 north at exit 200 to reach I-95 or to continue on to I-64 west of Richmond.

Each night, two cranes will remove the existing bridge deck and beams and set pre-cast bridge sections in its place. Workers will then secure the new structure to the previously-restored bridge substructure.

The following bridges have been replaced as part of the I-95 Richmond Bridge Restorations project:

  • Laburnum Avenue
  • Bridge over Boulevard exit ramp
  • Boulevard
  • Hermitage Road
  • Westwood Avenue
  • Overbrook Road
  • Sherwood Avenue
  • Robin Hood Road (southbound)

For more information about the I-95 Richmond Bridge Restorations project or to sign up for project updates, visit http://www.i95bridges.org. Anyone with questions about the project can call VDOT’s customer service center at 800-FOR-ROAD (800-367-7623).

Live traffic camera feeds and real-time listings of road conditions and closures in Virginia are available on VDOT’s 24-hour traffic and travel information website, www.511Virginia.org.  Information is also available by calling 511 or following the central Virginia 511 feed on Twitter @511centralVA.