April 27, 2010



WEEKDAY SCHEDULE CHANGE FOR I-95/395 REVERSIBLE LANES
Affects non-HOV times only for six months

CHANTILLY— The weekday schedule for the I-95/395 reversible lanes in northern Virginia will be slightly modified for the next six months to help ease construction-related delays, according to the Virginia Department of Transportation.  

From May 3 until November 1, the northbound high occupancy vehicle (HOV) lanes will close at 10 a.m. rather than 11 a.m. and the southbound HOV lanes will open at noon rather than 1 p.m., Mondays through Fridays.

The temporary schedule change will help ease delays on southbound I-95, where one lane is closed between the Fairfax County Parkway and Route 123 from 8 a.m. until 2 p.m. Monday through Thursday, and from 8 a.m. to noon on Fridays. The lane closure is part of the I-95 widening project.  

There is no change to the HOV-3 schedule:  HOV-3 (three persons in a vehicle) is in effect from 6 a.m. to 9 a.m. and from 3:30 p.m. to 6 p.m., Monday through Friday.



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.