NEW MATTOX CREEK BRIDGE OPENS IN WESTMORELAND COUNTY
Project replaced structurally deficient bridge on Route 205 near Colonial Beach

FREDERICKSBURG – Construction work was completed today on a new Mattox Creek bridge on Route 205 (James Monroe Highway) in Westmoreland County.

Temporary traffic signals were removed from the bridge this afternoon. Two travel lanes are now open to traffic on the bridge.

This estimated $9.6 million project replaced a structurally deficient bridge used by motorists traveling between Route 3 and the Town of Colonial Beach.

The new bridge has two 12 foot travel lanes and two 10 foot shoulders.

The project was finished ahead of the scheduled July 8, 2016 completion date. Construction on the bridge began in June 2014.

Abernathy Construction Corporation of Glen Allen, Va., was the project contractor.  

For more information on the project, please visit the project page on www.VirginiaDOT.org:

http://www.virginiadot.org/projects/fredericksburg/route_205_james_monroe_highway_bridge_replacement_at_mattox_creek.asp

(END)

 



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: May 20, 2016