I-95 WORK ZONES THIS WEEK AT FREDERICKSBURG
Motorists can expect northbound, southbound I-95 delays for paving, bridge construction

FREDERICKSBURG – Several nighttime work zones will be active on northbound and southbound Interstate 95 this week in the Fredericksburg area.

 

I-95 travelers are advised to use Route 1 or Route 301 to avoid delays. Message boards on I-95 will provide advance notice of lane closures and detour routes.

 

Crews are paving the interstate at several locations, and bridge construction is underway on a new overpass at Fall Hill Avenue.

 

Lanes will be closed at the following dates, times, and locations, weather permitting:

 

Tuesday, Sept. 8

 

  • Northbound I-95: Paving will be underway between Exit 136 (Centreport Parkway) and Exit 140 (Stafford/Route 630) in Stafford County. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 4:30 a.m.

 

  • Southbound I-95: Paving will be underway between Exit 126 (Spotsylvania) and Exit 118 (Thornburg) in Spotsylvania County. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 5 a.m.

 

Wednesday, Sept. 9

 

  • Northbound I-95: Bridge construction is underway at mile marker 131-132, just north of Exit 130 (Route 3) at Fredericksburg. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 4:30 a.m.

 

  • Northbound I-95: Paving will be underway between Exit 136 (Centreport Parkway) and Exit 140 (Stafford/Route 630) in Stafford County. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 4:30 a.m.

 

  • Southbound I-95: Paving will be underway between Exit 126 (Spotsylvania) and Exit 118 (Thornburg) in Spotsylvania County. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 5 a.m.

 

Thursday, Sept. 10

 

  • Northbound I-95: Bridge construction is underway at mile marker 131-132, just north of Exit 130 (Route 3) at Fredericksburg. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 4:30 a.m.

 

  • Northbound I-95: Paving will be underway between Exit 136 (Centreport Parkway) and Exit 140 (Stafford/Route 630) in Stafford County. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 4:30 a.m.

 

  • Southbound I-95: Paving will be underway between Exit 126 (Spotsylvania) and Exit 118 (Thornburg) in Spotsylvania County. Single lane closure starts at 9 p.m. Double lane closure 10 p.m. to 5 a.m.

 

511Virginia

 

Motorists can find real-time information about work zones, incidents and congestion on Virginia roads at 511Virginia.

 

Download the free mobile 511 app for Apple and Android devices to stay connected, or visit www.511Virginia.org. Motorists also can reach 511Virginia by calling 511 from any phone in Virginia.

(END)

 